Dashboard
Field Engineer / Dashboard
Tuesday, 1 September 2026

Welcome back, Jones Terfa

You have 3 tasks pending today and 1 weekly log due Friday. Isolo link restoration is currently ongoing.

File Patrol
3
Tasks Pending
+2 this wk
9
Tasks Completed
14
This Week's Activity
2
Patrols Filed

Today's Assigned Tasks

View log
Task IDActivityLocationPurposeStatus
ETNL-1042Core provisioningIsoloFor customersOngoing
ETNL-1043Fault clearanceIsoloLink restorationPending
ETNL-1039OTDR testingYaba PoPLink verificationPending

Weekly Progress

80%
4 of 5 days loggedWeek 1 (3rd–7th Sep)
Today, 8:00 AM
Submit Daily Activity Log before close of day (not required on Sundays).
Fri, 5 Sep
Weekly Activity Log due for Week ending 7 Sep.