Master Power to Airtel MSC
Team Lead / Projects / BOQ-10222
Back to Projects

Master Power to Airtel MSC

BOQ No. 10222 · Invoice No. 10222 · Client: WIOCC (via Emperor Telecoms Nigeria Ltd) · Ibadan, Nigeria · 23 Business Days (6 Jul–5 Aug 2026) · Ongoing

Master Power to Airtel — Civil & Fibre Deployment

10 tasks
S/NTask DescriptionAssigned ToProgressStartEndDurationStatusRemarks
1ROW Permits & Regularisation ApprovalTeam Lead
100%
6 Jul 20269 Jul 20264d Done Road authority approvals & WIOCC/Airtel permits
2Manhole Marking (10 No. at 250m intervals)Team Lead
100%
9 Jul 20269 Jul 20261d Done Mark all manhole positions along route
3Delivery of Materials to SiteTeam Lead
100%
9 Jul 20265 Aug 202620d Done Duct, cable, manhole materials
4Building of Manholes (10 No.)Team Lead
100%
16 Jul 202628 Jul 20269d Done 1x1x1.2m external, 0.7x0.7x1m internal
5Trenching (1m deep x 450mm wide)Team Lead
100%
13 Jul 202625 Jul 202610d Done Hand-trench
6Trench CastingTeam Lead
70%
31 Jul 20265 Aug 20264d Ongoing Hand-trench then pour concrete on the trench to secure places with shallow trenches.
7Thrustboring (Road Crossings & Pavements)Team Lead
100%
14 Jul 202627 Jul 202610d Done Concurrent with trenching
8Laying of Duct (1x40mm) – 2500mTeam Lead
100%
20 Jul 20265 Aug 202613d Done After trench/thrustbore completion
9Floating of 96F G.652D HDD Cable – 3000mTeam Lead
24%
29 Jul 202631 Jul 20263d Ongoing Terminate all 96-cores on WIOCC rack
10Splicing / Termination / DocumentationTeam Lead
0%
1 Aug 20263 Aug 20261d Pending 96-core termination, 30m slack each end, as-built docs
10
Total Manholes
9
Total Chains
2,474m
Total Distance
10/10
MH Casting Achieved

Work Quantity Summary

Total Trench
1,593m (1,588m done)
Trench Cast
667m (408m done)
Thrust Boring
219m (213m done)
Duct Laying
1,812m (1,801m laid)

Manhole-to-Manhole Segment Breakdown

10 MH · Master Power Entry MH – Airtel Entry MH
S/NFrom MHTo MHDistance (m)Trench (m)Trench Cast (m)Thrust Boring (m)Duct Laying/Laid (m)Status
1Airtel Entry VaultMH10 000 0/0Pending
2MH1MH2250 210400 250/250Done
3MH2MH3243 1337634 243/243Done
4MH3MH4265 02650 265/265Done
5MH4MH5259 1942738 259/259Done
6MH5MH6261 25506 261/0Ongoing
7MH6MH7245 1159436 245/245Ongoing
8MH7MH8249 24900 249/249Done
9MH8MH9392 21010181 392/392Ongoing
10MH9WIOCC Entry MH (MH10)305 2225924 305/305Ongoing
11WIOCC Entry MH (MH10)IBA06 Entry Vault5 550 5/0Pending
10
Total Manholes
2,474m
Total Distance
758m
Cable Pulled
0%
Joints Spliced

Cable Pulling Summary

Total Cable Pulling
2,474m
Cable Pulled
758m
Pending Cable
1,716m

Cable Pulling & Termination by Segment

HDD Cable Haul: 2500m · 96F G.652D
S/NFrom MHTo MHDistance (m)Cable Pulling (m)Cable Pulled (m)Pending Cable (m)Cable Status% Complete
1Airtel Entry VaultMH10 000 Pending0%
2MH1MH2250 2502500 Done100%
3MH2MH3243 2432430 Done100%
4MH3MH4265 2652650 Done100%
5MH4MH5259 2590259 Pending0%
6MH5MH6261 2610261 Pending0%
7MH6MH7245 2450245 Pending0%
8MH7MH8249 2490249 Pending0%
9MH8MH9392 3920392 Pending0%
10MH9WIOCC Entry MH (MH1)305 3050305 Pending0%
11WIOCC Entry MH (MH1)IBA06 Entry Vault5 505 Pending0%

Fibre Deployment Issue Log

4 issues logged
Issue RefDate RaisedRaised ByDescriptionReported ToAction TakenSeverityStatus
102220011 Jul 2026Contractor Community stopped the workers from carrying out civil work.Mr Ben Resolved by sending a certain amount of money4/5Resolved
1022200217 Jul 2026Ogheneochuko Behind schedule on Building Manholes. The Manhole casting time increased the speed at which the work is being done.3/5Resolved
1022200317 Jul 2026Ogheneochuko Thrustboring should have started but workers said they couldn't work the hard soil; deploying a TB machine to site instead. Reached out to the supervisor bringing the workers and resolved to bring another set of workers to site.4/5Resolved
1022200420 Jul 2026Ogheneochuko Distance of civil work given by the on-site supervisor differs from the client's work plan and our survey.Mr Ben and Lead Team Mr Ben and I visited the site on Tue 28 Jul to confirm the actual work on ground.4/5Resolved
Severity: 1 = Minor · 2 = Low · 3 = Moderate · 4 = High (schedule/cost at risk) · 5 = Critical (project-stopping)

Team A — Daily Production Target

6 Jul–27 Jul 2026
MetricExpected / DayAchievedVarianceStatus
Trench (m)500230-270OnHold
Thrust Boring (m)
Cable Pulling (m)
Joints / Splicing (No.)
Manhole Casting (No.)1
Only Team A is currently active on this project. Teams B–Z can be activated as headcount scales.
₦9.56M
Total Project Expense
₦12.0M
Budget
79.6%
Budget Used
₦2.44M
Budget Remaining

Expense by Category

CategoryAmount
Materials & Consumables₦1,344,000
Transport & Logistics₦540,000
ROW₦2,000,000
Business Development/Client Relations₦300,000
Contractors (Civil Work)₦5,250,000
Community Settlement₦123,000
TOTAL₦9,557,000

Verification Status

Verified Amount₦9,557,000
Unverified Amount₦0
79.6% of ₦12,000,000 budget used · ₦2,443,000 remaining